Project Jupiter (Stargate)

Under Construction

STACK Infrastructure / Oracle · Santa Teresa, NM

Maintained and reviewed by Malachi Rein, LEED AP BD+CDataset version

Summary

Project Jupiter (Stargate) by STACK Infrastructure / Oracle in Santa Teresa, NM is planned at 2.2 GW and about $165 billion, and is under construction, with a 2026 target as of September 2026. It ranks 11th of 54 tracked US mega projects by planned capacity, 2% of the 109.2 GW national total. The capacity figure is developer disclosed; the investment figure is bond authorization cap. Confidence is medium: one figure is reported, estimated, or scoped differently than the campus. Malachi.Energy tracks 2 mega projects in New Mexico in total.

Key figures

Planned capacity

2.2 GW

Developer disclosed

Announced investment

$165 billion

Bond authorization cap

Status

Under construction

As of September 2026

Target year

2026

First load or full build per source

Where the figures come from

Capacity basis
Developer disclosed
Investment basis
Bond authorization cap
Confidence
Medium: one figure is reported, estimated, or scoped differently than the campus.
Counted in headline totals
Yes. The investment figure is not developer-stated campus cost, so it is listed as announced rather than comparable spend.
Primary source
Daily Lobo, August 2026
Last verified
, dataset version 2026-09-14. Re-checked at every data refresh.

Basis and confidence definitions are in the directory methodology.

What is known

Stargate-affiliated mega campus in Dona Ana County, now cited at about $165B (matching the industrial revenue bonds approved over 30 years) and 2.2 to 2.5 GW. Initial operations targeted for Q4 2026 despite a denied gas pipeline, a pending air permit, and a state DOJ inquiry.

Location

Site
Santa Teresa, NM
Coordinates
31.78, -106.66
State directory
Data centers in New Mexico (17 verified facilities)

Other tracked projects in New Mexico

Cite this record

Rein, Malachi (2026). Project Jupiter (Stargate) (Santa Teresa, NM). In US Data Center Directory, dataset version 2026-09-14. Malachi.Energy. https://malachi.energy/data-centers/projects/project-jupiter-nm

@misc{malachienergy_project_jupiter_nm_2026,
  author = {Rein, Malachi},
  title = {Project Jupiter (Stargate) (Santa Teresa, NM)},
  howpublished = {US Data Center Directory, Malachi.Energy},
  year = {2026},
  note = {Dataset version 2026-09-14. Capacity basis: Developer disclosed. Investment basis: Bond authorization cap.},
  url = {https://malachi.energy/data-centers/projects/project-jupiter-nm}
}

All projects (JSON)All projects (CSV)Back to the directory

Figures are planned capacity and announced investment from public filings and reporting, not delivered power or audited spend. Capacity basis: developer disclosed. Investment basis: bond authorization cap. Dataset version . Maintained by Malachi Rein for Malachi.Energy.