SpaceXAI MACROHARDRR
OperationalSpaceXAI · Southaven, MS
Maintained and reviewed by Malachi Rein, LEED AP BD+CDataset version
Summary
SpaceXAI MACROHARDRR in Southaven, MS is planned at 250 MW and about $20 billion, and is operational, with a 2026 target as of October 2026. It ranks 51st of 56 tracked US mega projects by planned capacity, 0.2% of the 106.2 GW national total. The capacity figure is press or analyst reported; the investment figure is press reported. Confidence is medium: one figure is reported, estimated, or scoped differently than the campus. Malachi.Energy tracks 4 mega projects in Mississippi in total.
Key figures
250 MW
Press or analyst reported
$20 billion
Press reported
Operational
As of October 2026
2026
First load or full build per source
Where the figures come from
- Capacity basis
- Press or analyst reported
- Investment basis
- Press reported
- Nearest high-voltage transmission
- The campus sits 0.2 miles from the nearest 500 kV transmission line, owned by Entergy Mississippi Inc, per HIFLD transmission data current to September 2023, computed 2026-10-02. 12 line segments rated 230 kV or higher pass within 5 miles of the campus, the highest at 500 kV. Source: HIFLD
- Location basis
- Campus footprint identified. The coordinate marks the campus, so distance facts on this page are measured from it. Location source: DeSoto Times-Tribune, xAI buys building and additional land in Southaven for data center.
- Confidence
- Medium: one figure is reported, estimated, or scoped differently than the campus.
- Counted in headline totals
- Yes. The investment figure is not developer-stated campus cost, so it is listed as announced rather than comparable spend.
- Primary source
- Measured AI, June 2026
- Last verified
- , dataset version 2026-10-03. Re-checked whenever the project list is refreshed.
Basis and confidence definitions are in the directory methodology.
What is known
SpaceXAI's Mississippi building beside the Memphis Colossus campus, an 810,000 sq ft warehouse retrofit online since Q1 2026 with about 250 MW of IT compute. Mississippi announced the investment at more than $20B in January 2026, of which the data center is projected at more than $10B; a permanent 1.2 GW gas plant, permitted in March 2026, replaces temporary turbines through mid-2027.
Location
- Site
- Southaven, MS
- Coordinates
- 34.99, -90.03
- State directory
- Data centers in Mississippi (10 verified facilities)
Other tracked projects in Mississippi
- AWS MississippiMadison County, MS, 1.5 GW, operational
- Compass MeridianMeridian, MS, 500 MW, under construction
- AVAIO Digital BrandonBrandon, MS, 116 MW, under construction
Cite this record
Rein, Malachi (2026). SpaceXAI MACROHARDRR (Southaven, MS). In US Data Center Directory, dataset version 2026-10-03. Malachi.Energy. https://malachi.energy/data-centers/projects/xai-macrohardrr-southaven
@misc{malachienergy_xai_macrohardrr_southaven_2026,
author = {Rein, Malachi},
title = {SpaceXAI MACROHARDRR (Southaven, MS)},
howpublished = {US Data Center Directory, Malachi.Energy},
year = {2026},
note = {Dataset version 2026-10-03. Capacity basis: Press or analyst reported. Investment basis: Press reported.},
url = {https://malachi.energy/data-centers/projects/xai-macrohardrr-southaven}
}Figures are planned capacity and announced investment from public filings and reporting, not delivered power or audited spend. Capacity basis: press or analyst reported. Investment basis: press reported. Dataset version . Maintained by Malachi Rein for Malachi.Energy.