Data Centers in Indiana
14 verified facilities · about 45 estimated ·
Maintained and reviewed by Malachi Rein, LEED AP BD+CDataset version
Indiana data centers at a glance
As of October 2026, Indiana has 14 data centers verified in OpenStreetMap and an estimated 45 in total. That ranks 25th among the 48 states and territories in the directory and is 0.8% of all verified US facilities. Facilities cluster in Bloomington (1), Columbus (1), and Hammond (1). The largest operators by mapped sites are DartPoints (1), Digital Crossroad (1), and Indiana University (1), out of 4 named operators. Malachi.Energy also tracks 4 mega projects in Indiana totaling 5.8 GW of planned capacity and about $38 billion in announced investment, led by AWS Northwest Indiana (Amazon Web Services) in Hobart, IN, 2.4 GW and about $15 billion, under construction, targeted for 2027. Of the 3 tracked projects in Indiana with a site-level location, 2 sit within 5 miles of a 230 kV or higher transmission line, per HIFLD transmission data current to September 2023, computed 2026-10-02.
Facility counts: OpenStreetMap contributors (ODbL), scaled to Baxtel data center market directory totals. Mega projects: Malachi.Energy tally of public filings and announcements. Method notes on the methodology page. See also Indiana electricity rates.
Verified
14
OSM-mapped facilities
Estimated
~45
Scaled to industry totals
Top hub
Bloomington
1 verified facilities
Mega projects
5.8 GW
4 tracked, $38B announced
Map of data centers in Indiana
County boundaries, every verified facility, and tracked mega projects sized by planned capacity. Downloads carry the source line and dataset date for citation.
Top operators in Indiana
By OSM-verified facility count
- 1.DartPoints1
- 2.Digital Crossroad1
- 3.Indiana University1
- 4.Verizon Wireless1
Key hubs in Indiana
Cities with the most verified facilities
- 1.Bloomington1
- 2.Columbus1
- 3.Hammond1
- 4.New Palestine1
Mega projects in Indiana
4 tracked projects · 5.8 GW planned capacity · $38B announced
AWS Northwest Indiana (Hobart, IN)
Amazon Web Services
AWS's $15B Northwest Indiana expansion adding 2.4 GW of cloud and AI capacity. Hobart approved site plans in May 2026 and mass grading is underway; NIPSCO power deliveries begin January 2027.
Target: 2027Source: Inside Indiana Business (May 2026)Basis: developer disclosed MW, developer-stated campus costDetails & sources
AWS New Carlisle (New Carlisle, IN)
Amazon Web Services
AWS hyperscale campus in northern Indiana: 18 of 32 planned buildings operational and 14 under construction as of mid-2026, drawing about 2.25 GW at full buildout no earlier than late 2027. AWS said in July 2026 it had already invested $13.8B, above the $11B announced in 2024.
Target: 2027Source: Measured AI (Jun 2026)Basis: press or analyst reported MW, developer-stated campus costDetails & sources
Meta Lebanon (Lebanon, IN)
Meta
Meta's 1 GW campus in the LEAP Innovation District broke ground in February 2026: 13 buildings across 4M sq ft, with the first buildings online between late 2027 and early 2028.
Target: 2027Source: ConstructConnect (Apr 2026)Basis: developer disclosed MW, developer-stated campus costDetails & sources
Google Fort Wayne (Fort Wayne, IN)
Google's Fort Wayne campus: first building live December 2025, third phase (three more buildings) permitted March 2026 for construction from 2027 through 2030.
Target: 2030Source: Data Center Dynamics (Dec 2025)Basis: press or analyst reported MW, developer-stated campus costDetails & sources
All verified data centers in Indiana
14 facilities mapped in OpenStreetMap, sorted by city. Unnamed entries are mapped buildings tagged as data centers without a public name.
| Name | Operator | City | Address |
|---|---|---|---|
| IU Data Center | Indiana University | Bloomington | 2750 East Discovery Parkway |
| DartPoints Columbus | DartPoints | Columbus | 2425 Technology Boulevard |
| Digital Crossroad | Digital Crossroad | Hammond | 100 Digital Crossroad Drive |
| Amazon AWS Data Center | Unknown | New Carlisle | 31000 State Road 2 (address point) |
| Unnamed facility | Unknown | New Carlisle | 30750 Edison Road (address point) |
| Unnamed facility | Verizon Wireless | New Palestine | 7510 West Stinemyer Road |
| Agricultural and Biological Engineering | Unknown | West Lafayette | 225 South University Street (address point) |
| Learning GIS! | Unknown | West Lafayette | 625 Agriculture Mall Drive (address point) |
| Unnamed facility | Unknown | Unknown | Not listed |
| Unnamed facility | Unknown | Unknown | Not listed |
| Unnamed facility | Unknown | Unknown | Not listed |
| Unnamed facility | Unknown | Unknown | Not listed |
| Unnamed facility | Unknown | Unknown | Not listed |
| Unnamed facility | Unknown | Unknown | Not listed |
Frequently asked questions
How many data centers are in Indiana?
Indiana has 14 data centers verified in OpenStreetMap as of October 2026, and an estimated 45 in total once unmapped facilities are scaled in against Baxtel's industry count. That places it 25th of 48 states and territories by verified count.
Where are the data centers in Indiana?
The largest concentrations in Indiana are Bloomington with 1 verified facility, Columbus with 1 verified facility, Hammond with 1 verified facility, and New Palestine with 1 verified facility. The full table below lists every verified facility in the state with its operator and address.
Who operates the most data centers in Indiana?
By number of OSM-verified facilities, the largest data center operators in Indiana are DartPoints (1), Digital Crossroad (1), Indiana University (1), and Verizon Wireless (1). This ranks mapped sites, not megawatts, so a hyperscaler with many small buildings can outrank a colocation provider with one large campus.
What large data centers are being built in Indiana?
Malachi.Energy tracks 4 mega projects in Indiana as of October 2026: AWS Northwest Indiana (Amazon Web Services) in Hobart, IN, 2.4 GW and about $15 billion, under construction, targeted for 2027; AWS New Carlisle (Amazon Web Services) in New Carlisle, IN, 2.3 GW and about $11 billion, operational, targeted for 2027; Meta Lebanon in Lebanon, IN, 1.0 GW and about $10 billion, under construction, targeted for 2027; and Google Fort Wayne in Fort Wayne, IN, 200 MW and about $2 billion, operational, targeted for 2030. Together they total 5.8 GW of planned capacity and about $38 billion in announced investment. Figures are planned capacity from public filings and announcements, not delivered power.
Data centers in other states
Bordering Indiana
Most verified facilities
Facility data sourced from OpenStreetMap contributors (ODbL). Estimated totals scaled to Baxtel industry counts. Mega project data from public filings and announcements. Dataset last updated . Built by Malachi.Energy.